Akfen Renewables' wind projects with an installed capacity of 348.9 MWm are in operation.Akfen Renewable's Wind Projects constitute 49.9% of the Company's total installed capacity. In 2020, 2021 and 2022, the total generation was respectively 976 GWh, 1,050 GWh and 1,015 GWh.
Akfen Renewables has 7 wholly owned subsidiaries that operate Wind Power Plants: İmbat, Derbent, Isıder, Korda, Kovancı, Kanat and Pruva.
WPP facilities are covered by insurance policies, including extended machine breakdown insurance, loss of profit, third party liability and employer liability insurance.
1. Saritepe WPP
Sarıtepe WPP, located in Osmaniye and put into operation on 17.06.2016, has an installed capacity of 57 MWm/50 MWe. Sarıtepe WPP has been included in the assets of the Company on 05.02.2020 through the acquisition method. The electricity produced by this power plant is sold within the scope of FIT. Sarıtepe WPP will continue to benefit from FIT until 31.12.2026.
Production license for Sarıtepe WPP on behalf of İmbat was given on 11.06.2020 and is valid until 08.05.2057.
2. Demirciler WPP
Demirciler WPP, located in Osmaniye and put into operation on 22.07.2016, has an installed capacity of 23,3 MWm/23,3 MWe. Demirciler WPP has been included in the assets of the Company on 05.02.2020 through the acquisition method. The electricity produced by this power plant is sold within the scope of FIT. Sarıtepe WPP will continue to benefit from FIT until 31.12.2026.
Production license for Demirciler WPP on behalf of İmbat was given on 11.06.2020 and is valid until 15.07.2059.
Kocalar WPP
Kocalar WPP, located in Çanakkale province and commissioned on 14.03.2019, has an installed capacity of 30.6 MWm/26 MWe. The electricity produced by this power plant is sold within the scope of FIT. Kocalar WPP will continue to benefit from FIT until 31.12.2029.
The production license for Kocalar WPP was granted on 22.12.2011 and is valid until 22.12.2060.
Üçpınar WPP
Üçpınar WPP, located in Çanakkale province and commissioned on 11.05.2019, has an installed capacity of 112,2 MWm/ 99 MWe. The electricity produced by this power plant is sold within the scope of FIT. Üçpınar WPP will continue to benefit from FIT until 31.12.2029.
The production license for Üçpınar WPP was granted on 29.09.2011 and is valid until 29.09.2060.
Hasanoba WPP
Hasanoba WPP, located in Çanakkale province and commissioned on 02.08.2019, has an installed capacity of 51 MWm/ 51 MWe. The electricity produced by this power plant is sold within the scope of FIT. Hasanoba WPP will continue to benefit from FIT until 31.12.2029.
The production license for Hasanoba WPP was granted on 01.03.2012 and is valid until 01.03.2061.
Denizli WPP
Denizli WPP, located in Denizli and Aydın provinces and commissioned on 13.09.2019, has an installed capacity of 74,8 MWm/ 66 MWe. The electricity produced by this power plant is sold within the scope of FIT. Denizli WPP will continue to benefit from FIT until 31.12.2029.
The production license for Denizli WPP was granted on 18.08.2011 and is valid until 18.08.2060.
Some technical features of turbines of wind power plants are as follows:
Technical Properties | Üçpınar WPP | Kocalar WPP | Denizli WPP | Hasanoba WPP | Demirciler WPP | Sarıtepe WPP |
Turbine Producer | Siemens Gamesa | Siemens Gamesa | Siemens Gamesa | Siemens Gamesa | General Elektrik | General Elektrik |
Turbine Model | SWT-3.4-108 | SWT-3.4-108 | SWT-3.4-108 | SWT-3.4-108 | GE 2.85 103 / GE 1.7 103 | GE 2.85 103 |
Turbine Class | IEC Class IA | IEC Class IA | IEC Class IA | IEC Class IA | IEC Class S | IEC Class S |
Number of Turbines | 33 (3,4*33) | 9 (3,4*9) | 22 (3,4*22) | 15 (3,4*15) | 11 (2,85*4 + 7*1,7) | 20 (2,85*20) |
Hub Height (m) | 80 | 80 | 80 | 80 | 80 (GE 1,7) / 85 (GE 2,85) | 85 |
Rotor Diameter (m) | 108 | 108 | 108 | 108 | 103 | 103 |
There are ongoing applications for capacity increase of 93.6 MWm/ 92.4 MWe of WPP Projects. These Power Plants are Üçpınar WPP, Kocalar WPP, Hasanoba WPP, Sarıtepe WPP and Denizli WPP. The installed power applied for each WPP is respectively 9.6 MWe, 25 MWe, 25 MWe, 7.8 MWe, 25 MWe.
A total of 90.26 MWe Solar hybrid investments are made by constructing SPPs within 6 different WPPs.